Introduction

The client needed an In-Service Support (ISS) Basis of Estimate (BoE) & Work Breakdown Structure (WBS) and supporting WBS Dictionary that detailed specific tasks / deliverables which integrated with a Transition to Support (TtS) WBS and an Engineering WBS, which were currently in development.

The request was to:

  • Supply an independent view of the resourcing requirements for the In-Service Phase
  • Ensure that the client could distribute the right people promptly, with the right skill sets, for optimised resourcing of the future support program
  • Allow the client to seamlessly integrate our deliverable with the TtS and Engineering deliverables.

This required:

  • Consultations with all stakeholders
  • Development and agreement of format and structure
  • Generation of first draft for comment
  • Generation of final WBS & BOE.

Critical to Quality:

  • Organisation policy and guidance compliant
  • Alignment with current WBS and BOE for TtS and Engineering.

Timeline:

This project took 3 months to complete from Phase 1 (Voice of the Customer) to Phase 5 (Project Acceptance and Closure). One, Full Time Equivalent (FTE) person, worked the project.

Financial Benefits:

Under the traditional hiring model, this task would have needed; one external Suitably Qualified and Experienced Integrated Logistic Support Manager contractor, on a 6-month minimum term contract. Therefore we at TBES believe that by using the TBES model, a saving of contractor funding over a 3-month period, could be realised for this project.

Non-Financial Benefits:

  • Independent viewpoint
  • Completed in less time (when compared external contractor on min 6-month contract)
  • List of ‘Lessons Identified’ provided to client
  • List of risks supplied to client to add to the project risk register
  • List of concerns provided to client (as noted whilst working with the project documentation).

Client Testimonial

“…This culminated in a professional product, which is a huge benefit to a forward look into the resourcing of the team to enable the forward demand of the correct sub-functions at the correct level.”

At the end of the process the consultant created a comprehensive and beneficial closure statement, which continued their professional approach right to the end, providing further supporting information beneficial to the DT’s next steps. In all, a professional and effective experience which has added real value to the development of the platform support solution and the team.